Installation Instructions

1. Make a 2" incision, approximately 18" from the end of MaxCell pack. Pull out and cut off approximately 2 feet of pull-tape. Thus allowing the pull tape ends to retract back into the cells.

2. Using approximately 6 feet of pull tape, tie a non-slip knot to the incision. Then tie 3 to 6 half-hitch knots down to the end of MaxCell. Apply Vinyl tape over all knots and the end of MaxCell.

3. Using a Bow Line knot tie a swivel to the end of 3 feet pull tape. For multi-pack installations one swivel is sufficient, but stagger each MaxCell pulling head.

4. Using a Bow Line knot, attach the pull rope located in the rigid conduit to the other end of the swivel.

5. Install MaxCell.

6. Leave 3 to 5 feet of excess MaxCell in each manhole. Approx 1-2 feet from end of conduit cut a 2" incision in the edge of MaxCell then tie off to a stationary object located within the manhole.

7. Cut the MaxCell fabric above the incision; do not cut the pull tapes located within the cells. Leave 3-6 feet of pull tape in the manhole for cable installations.

8. At the opposite manhole gently pull MaxCell tight and tie off using procedures 6 and 7 above.